天天操天天射天天舔,午夜精品一码二码三码,欧美粗暴jizz性欧美20,日本视频中文字幕,国语对白新婚少妇在线观看,操大逼网站,国产精品麻豆三级一区视频

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager for the seller is told by her management that the project should do whatever possible to be awarded incentive money. The primary objective of incentive clauses in a contract is to:
A、reduce costs for the buyer.
B、help the seller control costs.
C、synchronize objectives.
D、reduce risk for the seller by shifting risk to the buyer.


相關試題

推薦文章
合作網(wǎng)站內(nèi)容