天天操天天射天天舔,午夜精品一码二码三码,欧美粗暴jizz性欧美20,日本视频中文字幕,国语对白新婚少妇在线观看,操大逼网站,国产精品麻豆三级一区视频

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The duration of a project is five months, The total cost initially allocated was US$30,000. The project is in the third month, The total expenditure in the project for the first two months is us$12,5000. The project is ahead of schedule and on budget for work completed.What is the cost variance of the project?
A、Greater than zero
B、Less than zero
C、Zero
D、One


相關(guān)試題

推薦文章