天天操天天射天天舔,午夜精品一码二码三码,欧美粗暴jizz性欧美20,日本视频中文字幕,国语对白新婚少妇在线观看,操大逼网站,国产精品麻豆三级一区视频

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Four months into a 10-month project, the project manager realizes that the project is behind schedule and slippage will lead to an overrun of 25% of the project’s budget. A change request is created, but when the project manager seeks approval, the executive is reluctant to do so. What could be the reason for this executive’s reluctance ?
A、Lack of the project management plan approval.
B、 Lack of the risk management plan approval.
C、 Lack of the communications management plan approval.
D、 Lack of the change management plan approval.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容