天天操天天射天天舔,午夜精品一码二码三码,欧美粗暴jizz性欧美20,日本视频中文字幕,国语对白新婚少妇在线观看,操大逼网站,国产精品麻豆三级一区视频

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The project team started to plan the activities for implementation project. The duration of the last three similar implementations was 7, 8 and 15 weeks respectively. What would be the expected duration for the new project according to PERT analysis?

A、8.5

B、9

C、10

D、12


相關試題

推薦文章